IMPORTANT POINTS TO REMEMBER FOR ‘PLUM CONCRETE’ WORK

IMPORTANT-POINTS-TO-REMEMBER-FOR-‘PLUM-CONCRETE’-WORK

Hi friends, i hope you all are doing good,

so i have come with this so called "important points to remember series" where i will be posting the some quick and important points to remember at the time of performing or at the time of inspection of activity. in short this is a quick quid to all the people who don't want to go in to much detail and want to have self help to tackle the practical life problems.

yes this points are always under correction because there may be different situation in your country or in any area which your living in. but as i always said that corrections are always welcome. you can mail me on person or through blog address. for any correction.

below are the list of some of the very common test and activity we perform on construction site. so according to your doubts just click on the below headings and you will get all your solutions in a quick pointers list. 

hope you like this content and yes i really appreciate if you subscribe to my website by just going at the bottom and fill your email. and you will receive my update of blogs on your mail.

so below are the points which are very important to remember for PLUM CONCRETE WORK at site.

1) Check raft area is dry for water tightness.

2) Proper layout as per drawings and details.

3) Making of level pads.

4) Weigh batcher etc. to be properly calibrated and checked before concreting.

5) Grade / mix of concrete to be properly controlled.

6) Make sure that no plum should be less than 160 mm.

7) Plum should no more than 20 %.

8) The plumb shall be distributed evenly and shall not closer than 150 mm. from the surface.

9) Curing is to be done after stipulated period.

THANK YOU SO MUCH , IF YOU LIKE THE CONTENT.