1. It is not necessary to design nominal reinforcement to
piles. Is it true?
Ans. In BS8110 and BS5400 Pt.4, they require the provision of
nominal reinforcement for columns. However, for pile design the requirement of
nominal reinforcement may not be necessary. Firstly, as piles are located
underground, the occurrence of unexpected loads to piles is seldom. Secondly,
shear failure of piles is considered not critical to the structure due to
severe collision. Moreover, the failure of piles by buckling due to fire is
unlikely because fire is rarely ignited underground.
However, the suggestion of provision of nominal
reinforcement to cater for seismic effect may be justified. Reference is made
to J P Tyson (1995).
2. How do rock sockets take up loads?
Ans. The load transfer mechanism is summarized as follows: When a
socketed foundation is loaded, the resistance is provided by both rock socket
wall and the socket base and the load distribution is a function of relative
stiffness of foundation concrete and rock mass, socket geometry, socket
roughness and strength. At small displacements the rock-socket system behaves
in an elastic manner and the load distribution between socket wall and socket
end can be obtained from elastic analysis. At displacements beyond 10-15mm,
relative displacement occurs between rock and foundation and the socket bond
begins to fail. This results in reduction of loads in rock-socket interface and
more loads are transferred to the socket end. At further displacements, the
interface strength drops to a residual value with total rupture of bond and
more loads are then distributed to the socket end.
3. In designing mini-piles, should the strength of grout be
neglected during assessment of
loading carrying capacity?
Ans.In designing min-piles, there are two approaches available:
(i) In the first approach, the axial resistance provided by
the grout is neglected and steel bars take up the design loads only. This
approach is a conservative one which leads to the use of high strength bars
e.g. Dywidag bar. One should note that bending moment is not designed to be
taken up by min-piles because of its slender geometry.
(ii) In the second approach, it involves loads to be taken
up by both grout and steel bars together. In this way, strain compatibility
requirement of grout and steel has to be satisfied.
4. What are the considerations in determining whether
casings should be left in for mini-piles?
Ans.Contrary to most of pile design, the design of min-piles are
controlled by internal capacity instead of external carrying capacity due to
their small cross-sectional area.
There are mainly two reasons to account for designing
mini-piles as friction piles:
(i) Due to its high slenderness ratio, a pile of 200mm
diameter with 5m long has a shaft area of 100 times greater than
cross-sectional area. Therefore, the shaft friction mobilized should be greater
than end resistance.
(ii) Settlements of 10%-20% of pile diameter are necessary
to mobilize full end bearing capacity, compared with 0.5%-1% of pile diameter
to develop maximum shaft resistance.
Left-in casings for mini-piles have the following
advantages:
(i) Improve resistance to corrosion of main bars;
(ii) Provide additional restraint against lateral buckling;
(iii) Improve the grout quality by preventing intrusion of
groundwater during concreting;
(iv) Prevent occurrence of necking during lifting up of
casings during concreting.
5. What is the purpose of post-grouting for mini-piles?
Ans. Post-grouting is normally carried out some time when grout
of the initial grouting work has set (e.g. within 24 hours of initial
grouting). It helps to increase the bearing capacity of mini-piles by enhancing
larger effective pile diameter. Moreover, it improves the behaviour of soils
adjacent to grouted piles and minimizes the effect of disturbance caused during
construction. In essence, post-grouting helps to improve the bond between soils
and grout, thereby enhancing better skin friction between them.
During the process of post-grouting, a tube with a hole at
its bottom is lowered into the pile and grout is injected. The mechanism of
post-grouting is as follows: the pressurized grout is initially confined by the
hardened grout and can hardly get away. Then, it ruptures the grout cover and
makes its way to the surrounding soils and into soft regions to develop an interlock
with harder soil zones. In order to enhance the pressurized grout to rupture
the initial grout depth, a maximum time limit is normally imposed between the
time of initial grouting and time of post-grouting to avoid the development of
high strength of initial grout. Consequently, the effect of soil disturbance by
installation of casings and subsequent lifting up of casings would be lessened
significantly.
6. In designing the lateral resistance of piles, should
engineers only use the earth pressure against pile caps only?
Ans. In some design lateral loads are assumed to be resisted by earth
pressure exerted against the side of pile caps only. However, it is
demonstrated that the soil resistance of pile lengths do contribute a
substantial part of lateral resistance. Therefore, in designing lateral
resistance of piles, earth pressure exerted on piles should also be taken into
consideration.
In analysis of lateral resistance provided by soils, a
series of soil springs are adopted with modulus of reaction kept constant or
varying with depth. The normal practice of using a constant modulus of reaction
for soils is incorrect because it overestimates the maximum reaction force and
underestimates the maximum bending moment. To obtain the profile of modulus of
subgrade reaction, pressuremeter tests shall be conducted in boreholes in site investigation.
Reference is made to Bryan Leach (1980).
7. In some codes, they limit the ratio of weight of hammer
to weight of pile for pile driving. What is the reason behind this?
Ans. When a hammer with initial motion collides with a stationary
pile, the transfer of energy is most efficient when the two masses are
comparable. That is the reason why some codes limit the ratio of weight of
hammer to the weight of pile to be more than 0.5. If the weight of hammer is
too low, most of energy during hammer driving is distributed to the hammer and
this causes tension induced in hammer and results in inefficient transfer of
energy.
8. Should engineers rely solely on Hiley’s formula in the
design of H-piles?
Ans. About 90% of H-piles adopt Hiley’s formula for design.
However, this formula is only applicable to pile lengths less than 30m and is
suitable for course-grained materials (not suitable to fine-grained soils) as
suggested by GEO (1996). In Hiley’s formula, by observing the penetration of
piles after the hammer impact, the pile capacity could be readily obtained from
the response of the impacting force. Therefore, the individual pile capacity
could be obtained by this dynamic method.
However, in normal foundation, groups of H-piles are present
and the soil foundation may not be able to support these H-piles simultaneously
even though individual piles are proven to have sufficient capacity by using
dynamic method. In this case, static method should be employed to ascertain if
the soil foundation could support these H-piles.
9. What is the function of drilling fluid in rotary drilling
in site investigation?
Ans.Drilling fluid in rotary serves two main purposes:
(i) Facilitate the rotation of drilling tube during rotary
drilling;
(ii) Act as a cooling agent to cool down heat generated
during drilling operation.
Traditionally, water is normally employed as drilling fluid.
However, it suffers from the following drawbacks:
(i) It affects the stability of nearby ground with the
introduction of water into the borehole (borehole for soil; drillhole for
rock);
(ii) It affects the quality of sample by changing the water
content of soil samples collected from the borehole/drillhole.
Substitutes are available in market to replace water as
drilling fluid (e.g. white foam).
10. What are the differences in function between rock
anchors and rock sockets?
Ans. Rock anchors are used primarily for resisting uplift forces.
On the contrary, rock sockets serve three main purposes:
(i) Rock socket friction and end bearing to resist vertical
load;
(ii) Passive resistance of rock sockets contribute to
resistance of lateral load; and
(iii) Socket shaft friction is also used for resisting
uplifting forces. But only 70% of this capacity should be used because of the
effect of negative Poisson ratio.
Note: Rock anchors, which may consist of a high tensile bar
or a stranded cable, are provided for tension piles when there are insufficient
soil covers to develop the required uplifting resistance.
11. What are the functions of cap block, drive cap and pile
cushion in driven piles?
Ans. Cap block is installed between the hammer end and the drive
cap to control the hammer blow in order to protect both the hammer and the pile
from damage. When the hammer hits the cap block, it compresses elastically and
reduces the peak forces, thereby lengthening the time of hammer blow. Moreover,
it should be capable of transmitting the hammer energy effectively to the
piles.
Drive cap is inserted at hammer tip to enhance uniform
distribution of hammer energy to the pile. Pile cushion is positioned between
the drive cap and the pile top. It intends to protect the pile from driving
stress induced during hammer blows. Moreover, it also serves to provide a
uniform driving load on top of the pile.
12.What is the significance of driving sequence of driven
piles?
Ans. For basement construction, if piles are driven from the
centre to the perimeter, there is a tendency of soils to move outwards. Such
lateral movement of soil may cause damage to nearby structures and utilities.
However, if piles are driven from the outside perimeter
inwards, there are little soil lateral movements. This results in a
well-compacted centre with an excess pore water pressure built up to resist the
loading of piles. Consequently, shorter pile lengths than the original designed
ones may result. However, some time after the pile driving operation, the
excess pore water pressure is dissipated and the shorter driven piles may not
be able to take up the original design loads. In this situation redriving is
required to drive the piles to deeper depths after dissipation of excess pore
water pressure.
13. What is the function of followers in driven H-piles?
Ans. A follower is an extension between the pile head and the hammer
that transfers the blow to the pile in which the pile head cannot be reached by
the hammer or is under water .For construction of driven piles, the piling
frame and hammer are normally erected on existing ground level but not at the
base of pile caps. However, H-piles are designed to be terminated near the base
of pile caps. If piles are driven at ground level, a certain length of H-piles
is wasted and cut when constructing pile caps. In this connection, pile
followers are used so as to save the wasted section of H-piles because
followers can be removed during subsequent construction of pile caps.
14. What are the advantages of using top-down approach in
basement construction?
Ans. The advantages of top-down approach are listed below:
(i) The structures above ground can be carried out
simultaneously with the structures below ground. This greatly reduces the time
for construction.
(ii) By using this approach, settlement can be reduced.
(iii) Since the permanent columns and slabs can be utilized
to support loadings during construction, it saves the cost of formwork.
Note: Top-down approach means construction of basement is
carried out from ground level downwards.
15. What are the methods to tackle negative skin friction?
Ans. (i) Use slender pile sections (e.g. H-pile or precast pile)
because smaller pile area when subject to the same working load would produce
higher deformation, thus increasing the relative downward movement of piles.
(ii) In a certain region of H-piles for ground water table
fluctuation, painting is applied on the surface of H-piles because the rise and
fall of water table contribute to the corrosion of H-piles. On the other hand,
to reduce the effect of additional loads brought about by negative skin friction,
bitumen is applied on the pile surface corresponding to the region of soils
that has negative skin friction. However, bitumen should not be applied to the
whole section of H-piles because it would be unable to derive the designed
frictional reaction from soils.
(iv) Design the piles as end-bearing so that they can take
up more load.
16. In piling works, normally founding levels of bored piles
are defined by using total core recovery or rock quality designation (RQD). Are
there any problems with such specification?
Ans. The use of total core recovery to determine the founding level
may not be able to indicate the quality of rock foundation for piles because it
depends on the drilling technique and drilling equipment (GEO (1996)). For
instance, if standard core barrels are used to collect samples, it may indicate
sufficient core recovery for samples full of rock joints and weathered rock. On
the other hand, if triple tube barrels are used for obtaining soil samples, samples
with joints and weathered rock can also achieve the requirements of total core recovery.
In case RQD is adopted for determining founding levels, it
may also result in incorrect results. For instance RQD does not indicate the
joints and infilling materials. Moreover, as it only measures rock segments
exceeding 100mm, rock segments exceeding 100mm is considered to be of good
quality rock without due consideration of its strength and joint spacing.
17. What are the head details of H-piles under compression
and subject to bending moment?
Ans. For steel sections referred to in BS5950, universal bearing pile
is characterized by having equal flange and web thickness while universal column
has different flange and web thickness. Universal columns can also be used as
bearing piles.
In the design of the head details of H-piles, there are
three typical cases to be considered, namely compression piles, tension piles
and piles with bending moment at the head in addition to tension or
compression. The design of these piles recommended by G. M. Cornfield (1968) is
listed below:
(i) Compression piles
For this type of piles, H-piles should be embedded 150mm in
concrete pile caps and it is not necessary to use any dowels and capping plates
in their connection.
(ii) Tension piles
A number of hook-ended bars are welded to the top of
H-piles.
(iii) Piles with bending moment at their head (tension or
compression)
The depth of embedment of piles into pile caps is substantially
increased and loads are transferred by horizontal bars welded to piles’
flanges.
18. In deep excavation, adjacent ground water table is drawn
down which may affect the settlement of nearby buildings. What is the remedial
proposal to rectify the situation?
Ans. One of the methods to control settlement of nearby buildings
due to excavation work is by recharging. Water collected in wells in deep
excavation is put back to the top of excavation in order to raise the
drawn-down water table. The location of recharge should be properly selected to
ensure the soil is sufficiently permeable to transfer the pumped water back
near the affected buildings.
19. What is the significance of quality of bentonite slurry
in the construction of diaphragm walls?
Ans. The quality of slurry plays an important role in the quality
of diaphragm walls. Firstly, if a thick slurry cake is formed in the interface
between slurry and in-situ soil, it has a tendency to fall off during
concreting works and it mixes with freshly placed concrete. Moreover, large
thickness of slurry cake would reduce the concrete cover and affect the future durability
performance of diaphragm walls.
20. During concreting of diaphragm walls, three tremie pipes
are used in one time. However, only one concrete truck is available. How should
the concreting works be carried out?
Ans. The most ideal situation is to supply each tremie pipe with
a single concrete truck. However, if only one concrete truck is available, all
the fresh concrete in the truck should not be placed in one single tremie pipe.
With all fresh concrete placed in one single tremie pipe while the others left
void, then due to the huge supply of concrete to the tremie pipe, a small
concrete hump may form at the base of the tremie pipe and it is likely that it
may collapse and trap the slurry inside the diaphragm walls. Therefore, the
fresh concrete should be evenly shared among the tremie pipes to avoid such
occurrence.
21. What is the purpose of conducting load test for piling
works?
Ans. Pile load test provides information on ultimate bearing
capacity but not settlement behavior. In essence, it can determine if the load
is taken up by the stratum designed or if the centre of resistance is at the
design location in piles as suggested by Robert D. Chellis (1961).
After conducting load tests, the curve of movement of pile
head (Settlement against load) and the curve of plastic deformation can be
plotted. By subtracting the curve of plastic deformation from the curve of pile
head movement at each load, the curve of elastic deformation can be obtained.
For piles of end-bearing type unrestrained by friction, the theoretical elastic
deformation can be calculated from e=RL/AE where e is elastic deformation, L is
pile length, A is area of pile, E is Young’s Modulus of pile material and
R is the reaction load on pile. By substituting e in the
formula, the elastic deformation read from the curve of elastic deformation, L
can be obtained which shows the location of the centre of resistance
corresponding to that load.
22. Why are vibrators not used in concrete compaction in
piling works?
Ans. Concrete for piles should be a high-slump self-compacting mix
which is capable of flowing between reinforcement cage with ease. Since
concrete is designed to be self-compacting, vibrators are not used for
providing further compaction. Moreover, the concrete in piles is compacted by
energy derived from free falling. However, if vibrators are used, the vibrated concrete
may be compacted to the sides of the concrete casings and hinders the lifting
up of casings. Reference is made to GEO (1996).
23. In Hiley’s formula for driven piles i.e. R=E/(s+0.5c),
why is a coefficient of 0.5applied for the term elastic deformation of piles
and soil?
Ans. Hiley’s formula is based on the principle of energy
conservation in which the energy brought about by hammers during the action of
hitting are transferred to piles in ground. When the hammer force and
displacement is plotted, the energy absorbed by piles is the area under the
curve. Since the curve of elastic component is linear with a positive slope, the
area i.e. energy should be the area of triangle (0.5xRxc) where R is reaction
force and c is elastic compression due to helmet, piles and soil system. For
settlement, it is of horizontal line in force-displacement diagram and hence
the energy transferred to pile-soil system is (Rxs).
24. For a rigid pile cap with vertical piles at the middle
and raking piles at the sides, what is the pattern of load distribution of
piles in such arrangement?
Ans. Due to the effect of interaction of individual piles, the
central piles tend to settle more than the edge piles when the pile cap is
under a uniform load. Therefore, raking piles at the edge take up a higher
fraction of total loads and are subject to higher axial and bending loads in case
the pile cap is stiff. In the extreme case, failure of these raking edge piles
may occur.
25. What are the problems associated with prestressed
concrete piles (Daido)?
Ans. The origin of Daido piles comes from Japan where these
prestressed concrete piles are used as replacement plies. Holes are pre-formed
in the ground and Daido piles are placed inside these pre-formed holes with
subsequent grouting of void space between the piles and adjacent ground.
However, in Hong Kong Daido piles are constructed by driving intoground by
hammers instead of the originally designed replacement method. Since the installation
method of Daido piles is changed, construction problems like deformation of pile
tip shoes, crushing of concrete at pile tip etc. occur. Reference is made to B.
W. Choy (1993).
26. Which one is a better choice, a large diameter piles or
a system of several smaller piles with the same load capacity?
Ans. The choice of a large diameter pile suffers from the
disadvantage that serious consequences would occur in case there is setting out
error of the pile. Moreover, in terms of cost consideration, for the same load
capacity the cost of a group of small diameter piles is generally lower than
that of a large diameter pile. On the other hand, for small diameter piles i.e.
mini-piles, they are advantageous in site locations with limited headroom and space.
In addition, in some structures with only a few piles, it is uneconomic because
of its high mobilization cost. Reference is made to Dr. Edmund C Hambly (1979).
27. What is the difference between capping beams and ground
beams for piles?
Ans. Capping beams for piles aim at transferring loads from
closely spaced columns or walls into a row of piles. On the other hand, ground
beams are beams provided between adjacent pile caps and they perform as
compression struts or ties in an attempt to prevent lateral displacement or
buckling of piles under uneven distribution of loads on pile caps. Both of them
have to be specially designed to cater for differential settlement of piles.
Capping beam performs the same functions as pile caps.
However, ground beams are structural elements to connect adjacent pile caps to
improve the stability of foundation.
28. In modeling a nonrigid mat foundation by using elastic
springs, should a uniform modulus of subgrade reaction be used along the whole
base of mat?
Ans. By using a bed of springs to simulate the flexible behaviour
of mat subject to loads, care should be taken in selection of the modulus of
subgrade reaction. In fact, the modulus of subgrade reaction depends on many
factors like the width of the mat, the shape of the mat, the depth of founding
level of the mat etc. In particular, the modulus of subgrade reaction is smaller
at the center while it is larger near the mat’s edges. If a constant modulus of
subgrade reaction is adopted throughout the width of the mat, then a more or
less uniform settlement will result when subject to a uniform load. However,
the actual behaviour is that settlement in the center is higher than that at
side edges. Consequently, it leads to an underestimation of bending moment by
18% to 25% as suggested by Donald P. Coduto (1994).
In general, a constant value of modulus of subgrade reaction
is normally applied for structure with a rigid superstructure and the rigid
foundation. However, a variable modulus of subgrade reaction is adopted instead
for non-rigid superstructure and non-dominance of foundation rigidity to
account for the effect of pressure bulbs.
29.What is the difference between direct circulation
drilling and reverse circulation drilling?
Ans. For direct circulation drilling and reverse circulation
drilling, the major difference in drilling method is related to the direction
of movement of drilling fluid. For direct circulation drilling, the drilling
fluid is circulated from the drill stem and then flows up the annulus between
the outside of the drill stem and borehole wall. The drilling fluid that carries
the drill cuttings flows to the surface and the subsequent settlement pits.
Pumps are employed to lift the cuttings free fluid back to the drill stem.
For reverse circulation drilling, the direction of flow of
drilling flow is opposite to that of direct circulation drilling. Drilling
fluid flows from the annulus between the drill stem and hole wall to the drill
stem. The drilling fluid is pumped to an nearby sump pits where cuttings are
dropped and settled.
30. What is the difference between “hammer efficiency” and
“coefficient of restitution” when using Hiley’s formula in pile driving?
Ans. Hammer efficiency refers to the ratio of kinetic energy of
the hammer to the rate energy (or potential energy). In essence, there is
undoubtedly certain energy losses induced by the hammer itself prior to the
actual impact on the driven pile. For instance, these losses may include
misalignment of the hammer, energy losses due to guiding friction, inaccurate dropping
height etc…
Coefficient of restitution refers to a value indicating the
strain energy during collision regained after the bodies reverted back to their
original shapes. If the coefficient of restitution is equal to unity, it means
that the collision is elastic and all energy has been returned after the impact
action. Hence, this is a index showing the degree the impact action in terms of
elasticity.
In mathematical forms,
Coefficient of restitution = -(v1-v2)/ (u1-u2)
Where u=initial velocity and v=final velocity after impact
Comments