IMPORTANT QUESTIONS AND ANSWERS RELATED TO REAL LIFE BRIDGE ENGINEERING PROBLEMS
1. Under what situation shall engineers use jacking at one
end only and from both ends in prestressing work?
Ans. During prestressing operation at one end, frictional
losses will occur and the prestressing force decreases along the length of
tendon until reaching the other end. These frictional losses include the
friction induced due to a change of curvature of tendon duct and also the wobble
effect due to deviation of duct alignment from the centreline. Therefore, the prestress
force in the mid-span or at the other end will be greatly reduced in case the frictional
loss is high. Consequently, prestressing, from both ends for a single span i.e.
prestressing one-half of total tendons at one end and the remaining half at the
other end is carried out to enable a even distribution and to provide symmetry
of prestress force along the structure.
In fact, stressing at one end only has the potential
advantage of lower cost when compared with stressing from both ends. For
multiple spans (e.g. two spans) with unequal span length, jacking is usually
carried out at the end of the longer span so as to provide a higher prestress
force at the location of maximum positive moment. On the contrary, jacking from
the end of the shorter span would be conducted if the negative moment at the
intermediate support controls the prestress force. However, if the total span
length is sufficiently long, jacking from both ends should be considered.
2. What is “preset” during installation of bridge bearings?
2. What is “preset” during installation of bridge bearings?
Ans. “Preset” is a method to reduce the size of upper plates
of sliding bearings in order to save the material cost. The normal length of an
upper bearing plate should be composed of the following components: length of
bearing + 2 x irreversible movement + 2 x reversible movement. Initially the
bearing is placed at the mid-point of the upper bearing plate without
considering the directional effect of irreversible movement. However, as irreversible
movement normally takes place at one direction only, the bearing is displaced/presetted
a distance of (irreversible movement/2) from the mid-point of bearing in which
the length of upper plate length is equal to the length of bearing +
irreversible movement + 2 x reversible movement. In this arrangement, the size
of upper plate is minimized in which irreversible movement takes place in one
direction only and there is no need to include the component of two
irreversible movements in the upper plate.
3. in incremental launching method of bridge construction,
what are the measures adopted to enhance sufficient resistance of the
superstructure during the launching process?
Ans. (i) during the launching process the leading edge of
the superstructure is subject to a large hogging moment. In this connection,
steel launching nose typically about 0.6-0.65 times span length is provided at
the leading edge to reduce the cantilever moment. Sometimes, instead of using
launching nose a tower and stay system are designed which serves the same
purpose.
(ii) The superstructure continually experiences alternative
sagging and hogging moments during incremental launching. Normally, a central
prestress is provided in which the compressive stress at all points of bridge
cross section is equal. In this way, it caters for the possible occurrence of
tensile stresses in upper and lower part of the cross section when subject to
hogging and sagging moment respectively. Later when the whole
Superstructure is completely launched, continuity
prestressing is performed in which the location and design of continuity
tendons are based on the bending moments in final completed bridge condition
and its provision is supplementary to the central prestress.
(iii) For very long span bridge, temporary piers are provided
to limit the cantilever moment.
4. In bridge widening projects, the method of stitching is
normally employed for connecting existing deck to the new deck. What are the
problems associated with this method in terms of shrinkage of concrete?
Ans. In the method of stitching, it is a normal practice to
construct the widening part of the bridge at first and let it stay undisturbed
for several months. After that, concreting will then be carried out for the
stitch between the existing deck and the new deck. In this way, the dead load
of the widened part of bridge is supported by itself and loads arising from the
newly constructed deck will not be transferred to the existing deck which is
not designed to take up these extra loads. One of the main concerns is the
effect of stress induced by shrinkage of newly widened part of the bridge on
the existing bridge. To address this problem, the widened part of the bridge is
constructed a period of time (say 6-9 months) prior to stitching to the
existing bridge so that shrinkage of the new bridge will take place within this
period and the effect of shrinkage stress exerted on the new bridge is
minimized.
Traffic vibration on the existing bridge causes adverse
effect to the freshly placed stitches. To solve this problem, rapid hardening
cement is used for the stitching concrete so as to shorten the time of setting
of concrete. Moreover, the stitching work is designed to be carried out at
nights of least traffic (Saturday night) and the existing bridge may even be closed
for several hours (e.g. 6 hours) to let the stitching works to left
undisturbed.
Sometimes, longitudinal joints are used in connecting new
bridge segments to existing bridges. The main problem associated with this
design is the safety concern of vehicles.
The change of frictional coefficients of bridge deck and
longitudinal joints when vehicles change traffic lanes is very dangerous to the
vehicles. Moreover, maintenance of longitudinal joints in bridges is quite
difficult.
5. What are the advantages of assigning the central pier and
the abutment as fixed piers?
Ans. (i) For abutment
pier to be assigned as fixed pier while the bridge is quite long, the longitudinal
loads due to earthquake are quite large. As the earthquake loads are resisted
by fixed piers, the size of fixed piers will be large and massive. In this connection,
for better aesthetic appearance, the selection of abutment as fixed piers could
accommodate the large size and massiveness of piers. Normally abutments are relatively
short in height and for the same horizontal force, the bending moment induced
is smaller.
(ii) For the central pier to be selected as the fixed pier,
the bridge deck is allowed to move starting from the central pier to the end of
the bridge. However, if the fixed pier is located at the abutment, the amount
of movement to be incorporated in each bearing due to temperature variation,
shrinkage, etc. is more than that when the fixed pier is located at central
pier. Therefore, the size of movement joints can be reduced significantly.
6. Sometimes the side of concrete bridges is observed to
turn black in colour. What is the reason for this phenomenon?
Ans. In some cases, it may be due to the accumulation of
dust and dirt. However, for the majority of such phenomenon, it is due to
fungus or algae growth on concrete bridges. After rainfall, the bridge surface
absorbs water and retains it for a certain period of time.
Hence, this provides a good habitat for fungus or algae to
grow. Moreover, atmospheric pollution and proximity of plants provide nutrients
for their growth. Improvement indrainage details and application of painting
and coating to bridges help to solve this problem. Reference is made to
Sandberg Consulting Engineers Report 18380/X/01.
7. In prestressing work, if more than one wire or strand is
included in the same duct, why should all wires/strands be stressed at the same
time?
Ans. If wires/strands are stressed individually inside the
same duct, then those stressed strand/wires will bear against those unstressed
ones and trap them. Therefore, the friction of the trapped wires is high and is
undesirable.
8. In the design of elastomeric bearings, why are steel
plates inserted inside the bearings?
Ans. For elastomeric bearing to function as a soft spring,
the bearing should be allowed for bulging laterally and the compression
stiffness can be increased by limiting the amount of lateral bulging. To
increase the compression stiffness of elastomeric bearings, metal plates are
inserted. After the addition of steel plates, the freedom to bulge is
restricted and the deflection is reduced when compared with bearings without
any steel plates under the same load. Tensile stresses are induced in these
steel plates during their action in limiting the bulging of the elastomer. This
in turn would limit the thickness of the steel plates.
However, the presence of metal plates does not affect the
shear stiffness of the elastomeric bearings.
9. How to determine the size of elastomeric bearings?
Ans. For elastomeric bearing, the vertical load is resisted
by its compression while shear resistance of the bearing controls the
horizontal movements. The design of elastomeric bearings are based on striking
a balance between the provision of sufficient stiffness to resist high
compressive force and the flexibility to allow for translation and rotation movement.
The cross sectional area is normally determined by the
allowable pressure on the bearing support. Sometimes, the plan area of bearings
is controlled by the maximum allowable compressive stress arising from the
consideration of delamination of elastomer from steel plates. In addition, the
size of elastomeric bearings is also influenced by considering the separation
between the structure and the edge of bearing which may occur in rotation because
tensile stresses deriving from separation may cause delamination. The thickness
of bearings is designed based on the limitation of its horizontal stiffness and
is controlled by movement requirements. The shear strain should be less than a
certain limit to avoid the occurrence of rolling over and fatigue damage. The
vertical stiffness of bearings is obtained by inserting sufficient number of
steel plates.
10. In a curved prestressed bridge, how should the guided
bearings in piers of the curved region be oriented with respect to the fixed
bearing in abutment?
Ans. To determine the orientation of guided bearings, one
should understand the movement of curved region of a prestressed bridge.
Movement of prestress and creep are tangential to the curvature of the bridge
(or along longitudinal axis) while the movement due to temperature and
shrinkage effects are in a direction towards the fixed pier. If the direction
of guided bearings is aligned towards the fixed bearing in the abutment, the
difference in direction of pretress and creep movement and the guided direction
towards fixed bearing would generate a locked-in force in the bridge system.
The magnitude of the lock-in force is dependent on the stiffness of deck and
supports. If the force is small, it can be designed as additional force acting
on the support and deck. However, if the force is large, temporary freedom of
movement at the guided bearings has to be provided during construction.
11. In the construction of a two-span bridge (span length =
L) by using span-by-span construction, why is a length of about 1.25L bridge
segment is constructed in the first phase of construction?
Ans. Basically, there are mainly three reasons for this
arrangement:
(i) The permanent structure is a statically indeterminate
structure. During construction by using span-by-span construction, if the first
phase of construction consists of the first span length L only, then the
sagging moment in the mid span of the partially completed bridge is larger than
that of completed two-span permanent structure.
To avoid such occurrence, 0.25L of bridge segment is
extended further from the second pier which provides a counteracting moment,
thereby reducing the mid-span moment of the partially completed bridge.
(ii) The position of 1.25 L countering from the first pier
is the approximate location of point of contraflexure (assume that the two-span
bridge is uniformly loaded) in which the bridge moment is about zero in the
event of future loaded bridge.
Therefore, the design of construction joint in this
particular location has the least adverse effect on the structural performance
of the bridge.
(iii) In case of a prestressed bridge, prestressing work has
to be carried out after the construction of first segment of the bridge. If the
prestressing work is conducted at the first pier which is heavily reinforced
with reinforcement, it is undesirable when compared with the prestressing
location at 1.25L from the first pier where there is relatively more space to
accommodate prestressing works.
12. What are the advantages of piers constructed
monolithically with the bridge deck over usage of bearings?
Ans. Basically, piers constructed monolithically with the
bridge deck are advantageous in the following ways:
(i) Movement of the bridge deck is achieved by the bending
deformation of long andslender piers. In this way, it saves the construction
cost of bearings by using monolithic construction between bridge deck and
piers. Moreover, it is not necessary to spend extra effort to design for
drainage details and access for bearing replacement. On the other hand, in
maintenance aspect substantial cost and time savings could be obtained by using
monolithic construction instead of using bearings as bridge articulation.
(ii) Monolithic construction possesses the shortest
effective Euler buckling length for piers because they are fixed supports at
the interface between bridge deck and piers.
13. Are diaphragms necessary in the design of concrete box
girder bridges?
Ans. Diaphragms are adopted in concrete box girder bridges
to transfer loads from bridge decks to bearings. Since the depth of diaphragms
normally exceeds the width by two times, they are usually designed as deep
beams. However, diaphragms may not be necessary in case bridge bearings are
placed directly under the webs because loads in bridge decks can be directly
transferred to the bearings based on Jorg Schlaich & Hartmut Scheef (1982).
This arrangement suffers from the drawback that changing of bearings during
future maintenance operation is more difficult.
In fact, diaphragms also contribute to the provision of
torsional restraint to the bridge deck.
14. What is the advantage of sliding bearings over roller
bearings?
Ans. In roller bearing for a given movement the roller
bearing exhibit a change in pressure centre from its original position by
one-half of its movement based on David J. Lee. However, with sliding bearing a
sliding plate is attached to the upper superstructure and the moving part of
bearing element is built in the substructure. It follows that there is no change
in pressure center after the movement.
15. What are the three major types of reinforcement used in
prestressing?
Ans. (i) Spalling reinforcement
Spalling stresses are established behind the loaded area of
anchor blocks and this causes breaking away of surface concrete. These stresses
are induced by strain incompatibility with Poisson’s effects or by the shape of
stress trajectories.
(ii) Equilibrium reinforcement
Equilibrium reinforcement is required where there are
several anchorages in which prestressing loads are applied sequentially.
(iii) Bursting Reinforcement
Tensile stresses are induced during prestressing operation
and the maximum bursting stress occurs where the stress trajectories are
concave towards the line of action of the load. Reinforcement is needed to
resist these lateral tensile forces.
16. Why is the span length ratio of end span/approach span
to its neighboring inner spans usually about 0.75?
Ans. From aesthetic point of view, an odd number of spans
with a decrease in length in the direction of abutment is desirable. Moreover,
spans of equal length are found to be boring.
However, the arrangement of
irregular span lengths is not recommended because it gives a feeling of
uneasiness.
From structural point of view, for a multi-span bridge with
equal span length, the sagging moment at the mid-span of the end span/approach
span is largest. In order to reduce this moment, the span length of end
span/approach span is designed to be 0.75 of inner spans.
However, this ratio should not be less than 0.40 because of
the effect of uplifting at the end span/approach span support.
17. In the design of a simply supported skew bridge, which
direction of reinforcement should be provided?
Ans. In the conventional design of steel reinforcement for a
simply supported skew bridge, a set of reinforcement is usually placed parallel
to free edge while the other set is designed parallel to the fixed edge.
However, this kind of arrangement is not the most efficient way of placing the
reinforcement. The reason is that in some parts of the bridge, the moment of resistance
is provided by an obtuse angle formed by the reinforcement bars which is ineffective
in resisting flexure.
In fact, the most efficient way of the arrangement of reinforcement
under most loading conditions is to place one set of bars perpendicular to the fixed
edge while placing the other set parallel to the fixed end as recommended by L.
A. Clark (1970). In this way, considerable savings would be obtained from the
orthogonal arrangement of reinforcement.
18. What are the functions of grout inside tendon ducts?
Ans. Grout in prestressing works serves the following
purposes:
(i) Protect the tendon against corrosion.
(ii) Improve the ultimate capacity of tendon.
(iii) Provide a bond between the structural member and the
tendon.
(iv) In case of failure, the anchorage is not subject to all
strain energy.
19. What is the consideration in selecting the orientation
of wing walls in the design of bridge abutments?
Ans. There are three
common arrangements of wing walls in bridge abutments based on Dr. Edmund C
Hambly (1979):
(i) Wing walls parallel to abutments
This is the simplest and shortest time to build but is not
the most economical design. This design has the advantage that it has least
disturbance to existing slope embankment.
(ii) Wing walls at an angle to abutments
This is the most economical design among the three options
in terms of material cost.
(iii) Wing walls perpendicular to abutments
Though it is not the most economical design, the wing walls
provide a continuous alignment with bridge decks which provide supports to
parapets. However, they cause disturbances to adjacent structures and utility
services during construction. Moreover, if the bridge is curved, the wing walls
may hinder the road curvature.
One the other hand, when the wing walls are structurally
connected to the abutment, then structural advantage can be taken by the
stability of box structure.
20. In joints of precast concrete bridge segments, what are the functions of applying epoxy adhesive?
Ans. Epoxy adhesive
is applied in these joints for the following purposes according to International
Road Federation (1977):
(i) It seals up the joints completely between precast
concrete segments to protect the prestressing tendons;
(ii) By filling voids and irregularities along the segment
joints, it helps to reduce stress concentrations otherwise it will be
developed; and
(iii) It helps in transferring of shear between the joints
in case a large single shear key is used.
21. Under what situation should engineers use pot bearings
instead of elastomeric bearings?
Ans. In the event of
high vertical loads combined with large angle of rotations, rubber bearings are
undesirable when compared with pot bearings. For instance, elastomeric bearings
require large bearing surfaces so that compression can be maintained between
the contact surfaces between the bearings and piers. Moreover, it also leads to
uneven distribution of stress on the piers and some of these highly induced
stresses may damage the piers. Consequently, pot bearings are better
alternatives than elastomeric bearings in such an scenario as suggested by
David J. Lee.
22. What are the shortcomings of grillage analysis which is
commonly used in structural analysis of bridges?
Ans. Grillage
analysis suffers from the following shortcomings based on E. C. Hambly:
(i) For coarse mesh, torques may not be identical in
orthogonal directions. Similarly, twists may differ in orthogonal directions.
(ii) Moment in any beams is mainly proportional to its
curvature only. However, moment in an element depends on the curvatures in the
beam’s direction and its orthogonal direction.
23. Polytetrafluoroethylene (PTFE) is commonly used in
sliding bearings. Why?
Ans. The choice of sliding surface of bearings is of vital
importance because the sliding surfaces generate frictional forces which are
exerted on the bearings and substructure of the bridge.
For instance, PTFE and lubricated bronze are commonly
choices of sliding surfaces for bearings. PTFE is a flurocarbon polymer which
possesses good chemical resistance and can function in a wide range of
temperature. The most important characteristic of this material is its low
coefficient of friction.
PTFE has the lowest coefficients of static and dynamic
friction of any solid with absence of stick-slip movement (David J. Lee). The
coefficient of friction is found to decrease with an increase in compressive
stress. However, PTFE do have some demerits like high thermal expansion and low
compressive strength.
In designing the complementary contact plate with PTFE
sliding surface, stainless steel plates are normally selected where the plates
should be larger than PTFE surface to allow movement without exposing the PTFE.
Moreover, it is recommended that the stainless steel surface be positioned on
top of the PTFE surface to avoid contamination of dirt and rubbish.
Lubricants are sometimes introduced to reduce the friction
between the PTFE surface and the upper stainless steel plate. Hence, the PTFE
may be designed with dimples to avoid the lubricant from squeezing out under
repeated translation movements.
24. Should raking piles of a bridge abutment be placed under
an embankment?
Ans. For a bridge
abutment to be supported on raking piles with different orientations, the movement
between the ground and the pile group is difficult to predict. For instance, if
some of the raking piles of the bridge abutment are extended beneath an
embankment, then the settlement of embankment behind the abutment may cause the
raking piles to experience severe bending moment and damage the piles as
recommended by Dr. Edmund C Hambly (1979).
25. How do engineer determine the number of cells for
concrete box girder bridges?
Ans. If the depth of
a box girder bridge exceeds 1/6 or 1/5 of the bridge width, then it is recommended
to be designed as a single cell box girder bridge. However, if the bridge depth
is smaller than 1/6 of the bridge width, then a twin-cell or multiple cell is a
better choice as suggested by Jorg Schlaich & Hartmut Scheef (1982).
However, one should note that even for wider bridges with small depths, the
number of cells should be minimized because there is not much improvement in
transverse load distribution when the number of cells of box girder is
increased to three or more.
26. What is sucker deck principle for variable depth bridge
decks?
Ans. For a variable
depth bridge deck, the depth of continuous multi-span bridge deck is increased
in pier supports and this absorbs sagging moments in the mid-span with the consequent
increase in hogging moments in pier supports. As a result, the mid-span depth can
be significantly reduced due to the reduction in sagging moment. In essence,
this sucker deck principle is applied in locations where headroom requirement
is of great concern. Moreover, in terms of structural performance, sucker decks
are effective in reducing dead loads than voided slab of equivalent uniform
depth for span length between 20-40m. In terms of aesthetics point of view, the
public tends to appreciate the structural form of arches and curved soffit rather
than boring uniform deck alignment. Reference is made to Brian Pritchard
(1992).
Comments