1) The area is to be cleaned properly before concreting.
2) Make sure that shuttering and reinforcement works are
done properly and checked (passed) by client/ consultant.
3) Check support for form work to be done properly and
staging for Concreting to be done properly.
4) Joints etc. In shuttering sealed properly before
proceeding with Concreting.
5) cut-outs and insert plate are to be provided in proper
position before pouring the concrete.
6) The machines and equipment’s (vibrator, mixer, batching,
and Concrete pump) are to be in good working condition.
7) If the concreting is done by pump, the pipe line and pump
are to be checked Before concreting.
8) Mix design for required grade to be controlled at mixer /
batching Manual.
9) Proper compaction is to be done by vibrating the
concrete.
10) Compacted area are to be levelled.
11) Cubes are to be taken at regular interval.
12) Slump test is carried out at regular interval.