IMPORTANT POINTS TO REMEMBER FOR ‘STONE FILLING’ WORK


hi friends, i hope you all are doing good,

so i have come with this so called "important points to remember series" where i will be posting the some quick and important points to remember at the time of performing or at the time of inspection of activity. in short this is a quick quid to all the people who don't want to go in to much detail and want to have self help to tackle the practical life problems.

yes this points are always under correction because there may be different situation in your country or in any area which your living in. but as i always said that corrections are always welcome. you can mail me on person or through blog address. for any correction.

below are the list of some of the very common test and activity we perform on construction site. so according to your doubts just click on the below headings and you will get all your solutions in a quick pointers list. 

hope you like this content and yes i really appreciate if you subscribe to my website by just going at the bottom and fill your email. and you will receive my update of blogs on your mail.

so below are the points which are very important to remember for STONE FILLING WORK at site.

1) Check raft surface is dry.

2) Make compartment (of 8 m x 8 m or as per site condition) of 9 inches thick

Brick work of required height.

3) Allow to set the brick work for min 7 days.

4) Lay two inches of grit (crushed sand) over the raft.

5) Lay average 200 mm high stone similar to soling.

6) Fill the voids properly with the metal.

7) Spread grit over the metal filling & run earth rammer.

8) Again do second layer of soling, metal filling, spread grit and run earth Rammer.

9) All operations are with dry material i.e. No addition of water.

THANK YOU SO MUCH , IF YOU LIKE THE CONTENT.
SUBSCRIBE FOR MORE SUCH INFORMATION ABOUT CIVIL ENGINEERING!!!!! 



 

Comments

your welcome to share your ideas with us in comments!

Archive

Contact Form

Send